Contractors

Project Status Reporter

Generate a professional, comprehensive project status report for owners and stakeholders that accurately communicates schedule, budget, quality, and risk status while protecting the contractor's contractual position.

This prompt generates a professional monthly project status report with an executive summary, color-coded Green/Yellow/Red status indicators for schedule, budget, and scope, detailed schedule and budget variance explanations, a scope change and pending change order section distinguishing approved from pending COs, accomplishments and planned activities, open issues formatted as specific decision requests with deadlines (protecting the contractor's schedule rights), a risk summary, and a safety and quality status section. All cost and schedule figures must match actual project records — presenting optimistic numbers that misrepresent project status creates contractual and professional liability. It is for general contractors submitting required owner reporting on commercial, institutional, or government construction projects.

Testedclaude-sonnet-4-6ValidatedMar 2026ScopeAll cost and schedule figures must match actual project reco…TierProfessional
AI Role
You are a construction project manager with expertise in owner communications an…
Models
Claude
Confidence
Professional
Constraints
All cost and schedule figures must match actual project records — never present optimistic figures that misrepresent project status
Pending change orders must be clearly distinguished from approved change orders to avoid misrepresentation of contract value
Issues requiring owner decisions must be clearly identified with response deadlines to protect contractor's schedule rights
Status indicators must be applied consistently — Red means action is required, not just that progress is slower than preferred
All figures must reference contract documents and project records as the source of truth
Tested Models
claude-sonnet-4-6
Uncertainty
If project data is incomplete or current figures are unavailable, insert [DATA REQUIRED FROM PROJECT CONTROLS] placeholders rather than estimating figures. Inaccurate status reports create more contractual risk than delayed reports.
Last updated
2026-05-28Published

The prompt

1,448 characters
project-status-reporter.prompt
You are a construction project manager with expertise in owner communications and project reporting. You understand how to present project status clearly and professionally while accurately representing the contractor's position on schedule, cost, and risk.

Generate a project status report for the following project:

Project Name: [PROJECT_NAME]
Owner: [OWNER_NAME]
Report Period: [DATE_RANGE]
Report Number: [REPORT_NUMBER]
Contract Completion Date: [ORIGINAL_DATE]
Forecast Completion Date: [CURRENT_FORECAST]
Schedule Variance: [AHEAD/BEHIND — DAYS]
Original Contract Value: [ORIGINAL_CONTRACT]
Approved Change Orders: [TOTAL_APPROVED_COs]
Pending Change Orders: [PENDING_CO_AMOUNT]
Current Contract Value: [CURRENT_CONTRACT]
Invoiced to Date: [TOTAL_BILLED]
Percent Complete (Schedule): [PERCENT]
Percent Complete (Cost): [PERCENT]
Work Performed This Period: [SUMMARY]
Work Planned Next Period: [SUMMARY]
Open RFIs: [COUNT]
Pending Submittals: [COUNT]
Open Issues: [DESCRIBE_KEY_ISSUES]
Safety: [INCIDENT_STATUS]
Quality Issues: [ANY_QUALITY_CONCERNS]

Generate a professional status report covering:
1. Project overview and reporting period summary
2. Schedule status with variance explanation
3. Budget/cost status with variance explanation
4. Scope changes and pending change orders
5. Key accomplishments this period
6. Planned activities next period
7. Open issues requiring owner decisions
8. Risk summary
9. Safety and quality status
WAITLIST

Runner beta coming — join the waitlist.

In-product execution isn't live yet. Leave your email and we'll let you know if the Runner beta opens.

How to use this prompt

1

Gather your current project data for all input fields, then generate the status report

2

Review all status indicators and ensure they accurately reflect current conditions

3

Have the PM review before submission to the owner

4

Submit per your contract reporting schedule.

Customization tips

Add a look-ahead section with a 30-60-90 day milestone forecast to give owners visibility into upcoming critical activities
Include a photo documentation section with 3-5 photos showing key work completed this period
Create a change order aging report within the status report to track how long pending COs have been awaiting approval
Add a subcontractor performance section if subcontractor issues are contributing to schedule or quality concerns

Sample output

Mar 2026Professional
Project Status Report — Monthly Owner Update Project: [Project Name] Report Period: [Month, Year] Date Prepared: [Date] Prepared by: [Project Manager Name], [General Contractor] Distribution: Owner, Owner's Representative, Architect PROJECT OVERVIEW: Project Description: [Brief description] Contract Value: $[Amount] (including approved change orders to date) Contract Substantial Completion Date: [Date] Current Forecast Substantial Completion Date: [Date — on schedule / [X] days [ahead/behind]] SCHEDULE STATUS: Overall progress: [X]% complete (per updated schedule) On critical path: [Describe current critical path activity — what is controlling the schedule today] Activities completed this period: [List 3-5 major activities completed] Activities planned next period: [List 3-5 major upcoming activities] Schedule risks: [Describe any current or emerging schedule risks] BUDGET STATUS: Original contract amount: $[Amount] Approved change orders to date: $[Amount] ([+/-X]%) Revised contract amount: $[Amount] Amount billed to date: $[Amount] ([X]% of revised contract) Pending change orders (not yet approved): $[Amount] Budget risk items: [Describe any items that may result in future change orders] QUALITY AND SAFETY: Safety: [Number] recordable incidents to date / [Number] days since last recordable incident Quality issues open: [Number] — [Brief description of any outstanding quality issues] Inspections completed this period: [List] Inspections failed/requiring re-inspection: [List, or "None"] OWNER ACTION ITEMS: The following items require owner decision or action to maintain the project schedule: 1. [Item] — Response required by [Date] — [Impact if delayed] 2. [Item] — Response required by [Date] — [Impact if delayed] PHOTOS: [Note that field photos are attached / available in project management platform]

Related prompts

Frequently asked questions

Read the Contractors AI Guide
Professional Disclaimer

Project status reports are project documentation that may be relied upon by owners for financial planning, schedule decisions, and dispute resolution. All figures must be accurate and consistent with project records. Consult contract documents for required reporting formats, frequency, and submission requirements. Legal review is recommended before submitting reports that address disputed items or potential claims.